Changes in the format of new connections

The CREG announced that these modifications will take effect as of July 6, 2023 and are aimed at designers, professionals and technicians of construction projects, who are interested in connecting a new property to the electrical network or modifying the existing connection./p>

What is a Special Connection?

  • It is a connection associated with more than 8 end accounts.
  • It requires a total load of more than 34 kW (Bogota) and more than 20 kW (other municipalities).
  • It has access to a Low Voltage network at a distance of more than 30m.

 

Special connections include the following stages and types of procedures that must be fulfilled to obtain the energy service.

  • Service feasibility request
  • Connection projects
  • Connection request
 

What is the process and requirements to request a connection?